pilipiliÂþ»­

 

News

» Go to news main

Campus Construction Update

Posted by Stephanie Rogers on June 19, 2017 in News

The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.

ALL STEAM WILL BE SHUT OFF JUNE 30TH

Week of June 19th – 30th
Interior

Week of June 19th

Piping installation to continue in LANGILLE, HALEY, JENKINS HALL, HANCOCK, EXTENSION ENGINEERING and BANTING building (Chance of minor noise with this work)

Piping in DAIRY building in women’s washroom and over adjacent offices/storage to start. This work will include core drilling through part of the wall and floor in the women’s washroom. (Expect disruption with some of this work).

Work in RUMINANT to relocate oil tank and electric DHW tank. (Domestic Hot Water will be shut down for ½ day for this work)

Electrical work to continue throughout buildings for equipment mounting and conduit runs. CHUTE, BOULDING, RUMINANT, LANGILLE, HALEY, JENKINS HALL, HANCOCK and EXTENSION ENGINEERING Buildings. (Chance of minor noise with this work, hammer drilling, etc.)

Isolation and draining to start in HANCOCK and EXTENSION ENGINEERING Buildings. (Note: heating will be shut off in these buildings)

Demolition to begin in Hancock and Extension Engineering. (Chance of minor noise with this work)

Work in the BANTING building will only consist of welding on the primary side of the piping.

Week of June 26th

Piping installation to continue in JENKINS HALL, HALEY, HANCOCK, EXTENSION ENGINEERING and BANTING Buildings. (Chance of minor noise with this work)

Piping in DAIRY building in women’s washroom and over adjacent offices/storage to start. This work will include welding cutting and grinding (Expect disruption with some of this work).

Work in the BANTING building will only consist of welding on the primary side of the piping.

Electrical work to continue throughout buildings for equipment mounting and conduit runs. CHUTE, BOULDING, RUMINANT, LANGILLE, HALEY, JENKINS HALL, HANCOCK and EXTENSION ENGINEERING Buildings. (Chance of minor noise with this work, hammer drilling, etc.)

Isolation and draining to start in HANCOCK and EXTENSION ENGINEERING Buildings. (Note: heating will be shut off in these buildings)

Demolition to begin in Hancock and Extension Engineering. (Chance of minor noise with this work)

Exterior

Restoration of Landscaping around Engineering Plant, Behind Haley Building, Along River Road,

Poultry Building and in Boulden RAC and Chute Buildings ongoing.

There will be Traffic Control in place for this work.

Testing Heating System Pipe

Restore Landscaping between Cummins and Jenkins Building

Restore Landscaping from Engineering Building to Dairy Building.

Clean up the areas disturbed from Engineering Building to Jenkins Hall.

Continue Traffic Control between Langille Athletic Center and Cox Institute (New)

Core through walls at Langille Athletic Center and Cox Institute (New).

Continue Excavation for pipe from Langille Center to Cox Institute (New).

Start installing pipe. This will include welding in the area.

Install Pipe at Cox Institute (New). This will include Welding in the area.

Backfill Pipe from Langille Athletic Center to Cox Institute (New).

Excavate for Pipe from Cox Institute to Cox Road.

Set up Road Closure on Cox Road from Cox Institute (New) to Cox Institute (Old)

Start Excavation for pipe along Cox Road.

Mass Excavation - Continuous dump truck traffic 7 am - 7 pm along River road and Farm Lane.

Ìý